Question: page completion 3. What is the payback and discounted payback period of project B? The discount rate is 9%. ProjectYear OYear 1 Year 2Year 3
page completion 3. What is the payback and discounted payback period of project B? The discount rate is 9%. ProjectYear OYear 1 Year 2Year 3 NPV 79.69 -300 150 150 150 -450 200 300 100 63.21 -350 300 100 50. 48.01 ? -250 100 250 0 19 -100 45 68 9.78 ABCDE O Last saved: 08:09:32 2 point(s) (no answer) Payback period is 2.00 years, discounted payback period is 2.83 years. Payback period is 1.83 years, discounted payback period is 2.18 years. Payback period is 2.83 years, discounted payback period is 2.76 years. Payback period is 1.83 years, discounted payback period is 2.31 years