Question: Parry is a project manager. He would risk doing things right instead of doing the right things, if he skips O considering the team members'

Parry is a project manager. He would risk "doing things right" instead of \"doing the right things," if he skips O considering the team members' planning and organizing skills. O clarifying the objectives when specic tasks are assigned as a group. 0 relating the project goals to overall organizational goals and strategy. 0 clarifying the scope of the project. Question 10 Which of the following statements is true about the shbone diagram? 0 [t is based on KJ analysis. 0 It consists of a line graph and a bar chart. 0 it determines the critical path taken to complete an activity. 0 it helps in identifying primary factors that affect issues in projects