Question: Part 1 ( 5 0 points ) : Solve the network for the Braves soccer team project. See page 3 for the project information. Note:
Part points: Solve the network for the Braves soccer team project. See page for the project information. Note: Save your MS Project file Part to show results and submit it for grading required
Enter the activities, predecessor information, activity duration, and solve the network using MS Project points
Identify the critical path pointsACFIKL
How long will the project take? points days
Which activitys have the maximum slack and the minimum slack? Indicate both free slack and total slack pointsH has the maximum free slack and total slack.
A C F I, K and L have the minimum free slack and total slack.
How sensitive is the network? Explain points