Question: Part 1 ( 5 0 points ) : Solve the network for the Braves soccer team project. See page 3 for the project information. Note:

Part 1(50 points): Solve the network for the Braves soccer team project. See page 3 for the project information. Note: Save your MS Project file (Part 1) to show results and submit it for grading (required).
Enter the activities, predecessor information, activity duration, and solve the network using MS Project (10 points).
Identify the critical path (10 points)_____A-C-F-I-K-L___________
How long will the project take? (10 points)______21 days___________
Which activity(s) have the maximum slack and the minimum slack? Indicate both free slack and total slack (10 points)__H has the maximum free slack and total slack. _
A, C, F, I, K and L have the minimum free slack and total slack. _
How sensitive is the network? Explain (10 points)______________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________
 Part 1(50 points): Solve the network for the Braves soccer team

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!