Question: part 1. construct the project activity network using AON methodology. part 2. assume that there is a maximum of eight resource hours per week available

part 1. construct the project activity network using AON methodology.
part 2. assume that there is a maximum of eight resource hours per week available for the project can you identify any weeks that have resource over commitments?
part 1. construct the project activity network
\begin{tabular}{|c|c|c|} \hline Activity & Duration & Prodecessars \\ \hline A & 3 & \\ \hline B & 5 & A \\ \hline C & 7 & A \\ \hline D & 3 & B, C \\ \hline E & 5 & B \\ \hline F & 4 & D \\ \hline G & 2 & C \\ \hline H & 5 & E.F,C \\ \hline \end{tabular} 3