Question: Part 1: Cost Control Earned Value Management (EVM) Check the following equations and answer the question below Earned Value (EV) = Planned Value (PV) *
Part 1: Cost Control Earned Value Management (EVM)
Check the following equations and answer the question below
Earned Value (EV) = Planned Value (PV) * Rate of Performance (RP)
Cost Variance (CV) = EV Actual Cost (AC)
Schedule Variance (SV) = EV PV
Cost Performance Indicator (CPI) = EV / AC
Schedule Performance Indicator (SPI) = EV / PV
Estimate at Completion (EAC) = Budget at Completion (BAC) / CPI
Estimate Complete Time (ECT) = Original time / SPI
Q1: Given the following information for a project with 14 months
PV = $20 000 EV = $ 27 000 AC = $21 000 BAC = $ 100 000
- Describe the project situation in terms of cost and schedule
- Calculate the EAC
- Calculate the ECT
Q2: Given the following information for a project with 14 months
PV = $26 000 EV = $ 19 000 AC = $28 000 BAC = $ 150 000
- Describe the project situation in terms of cost and schedule
- Calculate the EAC
- Calculate the ECT
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
