Question: Part 1 Create a Network Diagram for the following tasks: Task Predecessor A B A C B D B E B F C,D G E
Part 1
-
Create a Network Diagram for the following tasks:
| Task | Predecessor |
| A | |
| B | A |
| C | B |
| D | B |
| E | B |
| F | C,D |
| G | E |
| H | G |
| I | F,H |
Part 2
-
Based on the project diagram below:
-
List each project path and its duration.
-
What is the projects critical path?
-
Calculate the Forward and Backward Pass for the project. For each node calculate the Early Start, Early Finish, Late Start, Late Finish and Float.