Question: Part 1 : Initial Setup of the Documents Objective: Set up the initial AIA G 7 0 2 and AIA G 7 0 3 documents,

Part 1: Initial Setup of the Documents
Objective:
Set up the initial AIA G702 and AIA G703 documents, including the schedule of values, for a
simple construction project.
Instructions:
1. Your company has been awarded a contract to construct a new residence for the Munster
residence at 1313 Mockingbird Lane, Mockingbird Heights, GA 30144.
2. Project Overview:
o Contract Value: $250,000
o Start Date: 3/1/2025
o Project Duration: 6 months
o Work Breakdown: 10 line items (listed below).
o Retainage Percentage: 10% on both completed work and stored materials.
3. Steps:
o Step 1: Review the AIA G703(Continuation Sheet) form.
Create a schedule of values based on the provided line items and contract
value.
Enter the scheduled value for each line item (provided below) into the
AIA G703 form.
o Step 2: Review the AIA G702(Application and Certificate for Payment) form.
Set up the document by entering the contract value and other basic
information (leave columns for work completed, previous payments, and
stored materials blank for now).
4. Line Items for Schedule of Values:
Item Description Scheduled Value
1. Site Work $30,000
2. Foundation $40,000
3. Framing $50,000
4. Roofing $20,000
5. Electrical $30,000
6. Plumbing $20,000
7. HVAC $25,000
8. Windows $10,000
9. Interior Finishes $15,000Steps:
10. Landscaping $10,000
Step 1: Complete the AIA G703(Continuation Sheet) by entering the work
completed and materials stored for each line item.
Calculate the retainage (10%) on both completed work and stored
materials.
Step 2: Complete the AIA G702 form.
Transfer the total values from the G703 form to the G702 form.
Calculate the total amount due for this billing period, considering the
previous payments, retainage, and current work/materials billed.
Deliverables for Part 2:
Completed AIA G702 and G703 forms with the work completed, stored materials,
and amounts due for the third billing period.
Save the G702 and G703 forms in PDF format
Upload Part 2 of the Assignment to D2L
Part 1 : Initial Setup of the Documents

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!