Question: Part 1 of 2 -- Build a table First, let's practice a simple problem: Build ONE basic table to have it ready to sell on

Part 1 of 2 -- Build a table First, let's

Part 1 of 2 -- Build a table First, let's practice a simple problem: Build ONE basic table to have it ready to sell on Day 7. Compute when you'll need to procure each component. Enter the quantity in the right cell. The Day 7 sale is already done for for. Then, go to the next sheet to build a Tesla! Note: None of the items have lot-size requirements nor safety stock. Day Demand 1 2 3 5 7 8 9 10 11 12 13 Tables 1 Orders Tables Top Legs Bill of Materials Table Procurement Lead Time Top 2 days Legs 3 days Top (1) Legs (4) Production Lead Time Table 1 day