Question: Part 1 Question 1 A project manager is dealing with a venture. The first extension standard of the venture was planned at $100,000. Since work
Part 1
Question 1
A project manager is dealing with a venture. The first extension standard of the venture was planned at $100,000. Since work on the venture began there have been seventeen approved and affirmed changes to the venture. The progressions have an estimation of $17,000 and the cost of exploring them before their endorsement was $2,500. What is the present spending plan for the venture?
Question 2
A project manager is dealing with a venture that has achieved the end of planning phase. The work scope has been consented to and conclusive cost gauges have been finished for the venture. The aggregate assessed cost of the venture is $100,000. It is sensible to expect that the venture won't cost over which value?
Part 2
1.What are serial bonds?
2.________ is a form of long-term debt often issued by large corporations especially public utilities when constructing large, expensive power plants for generating electricity.
3.What is bond discount?
4.What is NPV?
5.The __________is the interest rate that willdiscountan investment's future cash amounts so that the sum of the present values will be equal to cash paid at the beginning of the investment.
6.How do you calculate NPV?
7.What is the purpose of thecash flow statementorstatement of cash flowsorSCF?
8.Name classifications in which major cash flows are presented.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
