Question: Part 1 : Update all initiation and planning tasks as being 1 0 0 % complete and to Planned Values. Part 2 : Review the
Part :
Update all initiation and planning tasks as being complete and to Planned Values.
Part :
Review the Topic project information file for Execution Actual durations and use the Mark on Track Update Task function.
Procure hardware from suppliers
Obtain software OS licenses
Obtain software application licenses
Setup test area
Load software onto pilot machines
Validate functionality
Configure production hardware
Deploy production hardware
Load software to deployed hardware
Validate startup on deployed hardware
Perform OS testing
Perform application testing
Obtain formal signoff from users
Accounting mistakes must be corrected.
Project Manager: $ per hour
Software Engineer: $ per hour
What is the cost variance, schedule variance, cost performance index CPI and schedule performance index SPI and TCPI for the project?
Is the project ahead of schedule or behind schedule? Is the project under budget or over budget?
Use the CPI to calculate the estimate at completion EAC for this project. Is the project performing better or worse than planned?
Use the SPI to estimate how long it will take to finish this project.
Part :
As the project management team, you need to analyze the data from Parts and of the assignment to assess the following.
Are there issues that need to be escalated?
Is it acceptable to do nothing and simply proceed?
Should the project be terminated?
Based on your evaluation of the threats to the project, how should you proceed?
Based upon the results of the data review, develop a status report for your project sponsor.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock