Question: Part 1 Using the below rate information and duration information, calculate a schedule and budget estimate for your project, based on resources you had allocated
Part 1 Using the below rate information and duration information, calculate a schedule and budget estimate for your project, based on resources you had allocated during week 4 tutorial.
| Project Sponsor | 120/hr |
| Program Manager | 120/hr |
| Project Manager | 110/hr |
| QA Manager | 110/hr |
| Business Process Manager | 110/hr |
| 2* Business Analysts | 90/hr |
| Technical Lead | 90/hr |
| Technical Architect | 90/hr |
| Solution Architect | 90/hr |
| Training Lead | 90/hr |
| 3* Trainers | 70/hr |
| Test Team Lead | 90/hr |
| 2* Testers | 70/hr |
| Development Team Lead | 90/hr |
| 4* Developers | 70/hr |
| Web Designers | 70/hr |
| Project Name | Level 2 | Level 3 | Duration |
| 1.1 Initiation | 1.1.1 Evaluation & Recommendations | 3 weeks | |
| 1.1.2 Develop Project Charter | 3 weeks | ||
| 1.1.3 Deliverable: Submit Project Charter | 5 days | ||
| 1.1.4 Project Sponsor Reviews Project Charter | 3 days | ||
| 1.1.5 Project Charter Signed/Approved | 2 days | ||
| 1.2 Planning | 1.2.1 Create Preliminary Scope Statement | 5 weeks | |
| 1.2.2 Determine Project Team | 5 weeks | ||
| 1.2.3 Project Team Kickoff Meeting | 5 days | ||
| 1.2.4 Develop Project Plan | 3 weeks | ||
| 1.2.5 Submit Project Plan | 2 weeks | ||
| 1.2.6 Milestone: Project Plan Approval | 1 week | ||
| 1.3 Execution | 1.3.1 Project Kickoff Meeting | 5 days | |
| 1.3.2 Verify & Validate User Requirements | 3 weeks | ||
| 1.3.3 Design System | 7 weeks | ||
| 1.3.4 Procure Hardware/Software | 2 weeks | ||
| 1.3.5 Install Development System | 1 week | ||
| 1.3.6 Testing Phase | 5 weeks | ||
| 1.3.7 Install Live System | 3 weeks | ||
| 1.3.8 User Training | 2 weeks | ||
| 1.3.9 Go Live | 1 week | ||
| 1.4 Control | 1.4.1 Project Management | --------- | |
| 1.4.2 Project Status Meetings | --------- | ||
| 1.4.3 Risk Management | --------- | ||
| 1.4.4 Update Project Management Plan | --------- | ||
| 1.5 Closeout | 1.5.1 Audit Procurement | 2 weeks | |
| 1.5.2 Document Lessons Learned | 2 weeks | ||
| 1.5.3 Update Files/Records | 1 week | ||
| 1.5.4 Gain Formal Acceptance | 1 week | ||
| 1.5.5 Archive Files/Documents | 1 week |