Question: Part 2: Based on your model in Part 1, modify it to fulfil the following new conditions. Conditions: . All transfer times between any
Part 2: Based on your model in Part 1, modify it to fulfil the following new conditions. Conditions: . All transfer times between any two Processes, between Create and Process 1, and between Process 3 and Dispose are now UNIF (2,3) minutes. Parts leaving Process 1 will instantly enter a Cool-down Zone (Storage) and wait for 10 minutes before being transferred to Process 2. Make it runs for 16,000 minutes with one replication. Save and upload your answer as Part2.doe. Requirements: Animate the entity transfer with Station and Route. Animate the cool-down process with Store, Delay, Unstore. Questions: I. How many parts have been processed at the end of the simulation? II. What is the average utilisation level of Workstation 2? III. On average, how long does it take for a part to pass through the system?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts