Question: Part 2 Budget Estimating (30 points) Using the same scenario from the previous unit on scheduling, create a time-phased budget for the following project. Prepare
Part 2 Budget Estimating (30 points)
Using the same scenario from the previous unit on scheduling, create a time-phased budget for the following project. Prepare a figure like Exhibit 10.9, CPT 4e, that illustrates the daily and cumulative costs for the resource-leveled project.
Assume the following hourly rates:
Alcides $45 / hr.
Joan $50 / hr.
(Assume normal workday = 8 hours/day & normal workweek = 40 hours/week)
| Activity ID | Activity | Immediate Predecessor | Duration in days | Resource | Work Hours available per Day |
| A | Evaluate freezers |
| 2 | Alcides | 6 |
| B | Chart temperatures |
| 6 | Joan | 4 |
| C | Review service record |
| 2 | Alcides |
|
| D | Consult with HVAC engineer | A, B, C | 3 | Alcides |
|
| E | Develop construction plan | D | 10 | Joan |
|
| F | Complete IC assignment | E | 2 | Alcides |
|
| G | Complete ROI analysis | E | 5 | Joan |
|
| H | Conduct regulatory review | E | 4 | Joan |
|
| I | Obtain construction approval | F, G, H | 2 | Alcides |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts