Question: PART 3 ( 2 5 % of the assignment ) Case Study A Teesside PLC has won a contract to work on a major Project

PART 3(25% of the assignment)
Case Study
A Teesside PLC has won a contract to work on a major Project to start on 1st November 2024. As a Project Manager you need to develop and analyse the planning schedule for this project using MS-Project. Your project team has identified major activities of the project, their dependency and resources needed to run each activity (see Appendix 1).
Appendix 1 provides information about the project, which includes project logic (activity links and their relationship finish to start (FS), start to start (SS), and start to finish (SF)), activity durations, resource allocation and work breakdown structure (WBS).
You have been asked to perform the following planning and scheduling processes using Microsoft Project 2012 or later version.
A: CPM & WBS (10% of the assignment)
1. DrawaGantt-ChartandCPMnetworkfortheproject.Calculateearlystart(ES),early finish (EF), late start (LS), late finish (LF) and total float (TF) based on As Soon as Possible (ASAP) method and identify critical path.
Page 3 of 10
Advanced Project Planning & Visualisation Assignment
School of Computing, Engineering and Digital Technologies, Teesside University
2. Draw WBS for the project (must include Level 1, Level 2, Level 3 and Level 4) and discuss the importance of WBS as a Project Management tool.
3. Explain why identification of the critical path is important? Also comment on the changes to the Critical Path, if the project is developed using As Late as Possible (ALAP) method.
B: Resource Planning (10% of the assignment)
1. Produce and draw smoothed resource histograms for the skilled labour resources used in the project. Critically assess the output identifying the maximum units of each resource required for this project.
2. Carry-out resource levelling for Unskilled resource only (do not use automatic resource levelling) and discuss how activities might be delayed beyond LST to cater for the limits on Unskilled resources as a result of levelling. Consider resource pool for unskilled resources as 7 units per day.
3. Explainanddiscusstheprocessofresourcelevelling.
C: Cost Analysis (5% of the assignment)
1. Calculatethecostofeachactivityintheproject(level3).Considerthestandardcost of a skilled labour as 20/hr, unskilled labour as 10/hr and equipment as 50/hr.
2. Producecumulativecost-timecurvefortheproject.
Note:
Start the project on 1st November 2024.
Use default UK working calendar (i.e. Saturdays and Sundays are non-working
days, 8 working hours in a day, bank holidays should be considered as non-
working days)
Use resource unit as decimal.
Use fixed duration and set unit as days.
Clearly identify each part of the answers to the questions.
Use captions and axis labels to clearly indicate what each chart/graph is showing.
 PART 3(25% of the assignment) Case Study A Teesside PLC has

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!