Question: PART 3 ( 2 5 % of the assignment ) Case Study A Teesside PLC has won a contract to work on a major Project
PART of the assignment
Case Study
A Teesside PLC has won a contract to work on a major Project to start on st November As a Project Manager you need to develop and analyse the planning schedule for this project using MSProject. Your project team has identified major activities of the project, their dependency and resources needed to run each activity see Appendix
Appendix provides information about the project, which includes project logic activity links and their relationship finish to start FS start to start SS and start to finish SF activity durations, resource allocation and work breakdown structure WBS
You have been asked to perform the following planning and scheduling processes using Microsoft Project or later version.
A: CPM & WBS of the assignment
DrawaGanttChartandCPMnetworkfortheproject.CalculateearlystartESearly finish EF late start LS late finish LF and total float TF based on As Soon as Possible ASAP method and identify critical path.
Page of
Advanced Project Planning & Visualisation Assignment
School of Computing, Engineering and Digital Technologies, Teesside University
Draw WBS for the project must include Level Level Level and Level and discuss the importance of WBS as a Project Management tool.
Explain why identification of the critical path is important? Also comment on the changes to the Critical Path, if the project is developed using As Late as Possible ALAP method.
B: Resource Planning of the assignment
Produce and draw smoothed resource histograms for the skilled labour resources used in the project. Critically assess the output identifying the maximum units of each resource required for this project.
Carryout resource levelling for Unskilled resource only do not use automatic resource levelling and discuss how activities might be delayed beyond LST to cater for the limits on Unskilled resources as a result of levelling. Consider resource pool for unskilled resources as units per day.
Explainanddiscusstheprocessofresourcelevelling.
C: Cost Analysis of the assignment
CalculatethecostofeachactivityintheprojectlevelConsiderthestandardcost of a skilled labour as hr unskilled labour as hr and equipment as hr
Producecumulativecosttimecurvefortheproject.
Note:
Start the project on st November
Use default UK working calendar ie Saturdays and Sundays are nonworking
days, working hours in a day, bank holidays should be considered as non
working days
Use resource unit as decimal.
Use fixed duration and set unit as days.
Clearly identify each part of the answers to the questions.
Use captions and axis labels to clearly indicate what each chartgraph is showing.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
