Question: Part 3. Perform risk analyses for the project. (20 marks) Your team has identified several key aspects for the project. The following table shows the
Part 3. Perform risk analyses for the project. (20 marks)
Your team has identified several key aspects for the project. The following table shows the base-case assumptions, together with the best case and worst case.
Parameter Initial Assumption Worst Case Best case
First-year sales
(as a percentage of the total
revenues in the latest reporting period) 7% 4% 10%
Revenue growth rate 15% for the second year, 10% for the third, Constant after the first Constant after the first year at 15% rate
and 5% annually for the final two years year at a rate of 0%
Project's EBITDA/Sales profit margin Similar to existing projects. +5% to the initial assumption -5% to the initial assumption
Net Working Capital $25,000,000 $35,000,000 $15,000,000
Beta The estimated beta The upper bound of 95% The lower bound of the 95% confidence interval confidence Interval confidence interval
(a) Perform break-even analysis with respect to the first-year sales parameter.
(b) Perform sensitivity analysis for each parameter. Evaluate which parameter is the most important to the project.