Part Process Analysis
The new computer controlled NCX machine has replaced older machines. Before the replacement,
each part required two minutes of processing on the first machine, then eight minutes of processing
on the second machine, and finally four minutes on the third. Each of these machines had a dedicated
operator. The new NCX machine can do all steps in minutes per part. Please help answer questions through
Question
The capacity for the first machine in the initial configuration was:
A unitsminute
B unitsminute
C unitsminute
Question
The bottleneck in the initial configuration was:
A the second machine
B the first machine
C the third machine
Question
As a result of the introduction of the NCX the cycle time for this process has:
A increased
B decreased
C not changed
Question
As a result of the introduction of the NCX the flow time for this process has:
A decreased
B increased
C not changed
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock