Question: Part 4: Series Method (40 points) Solve this resource scheduling problem with the series method. The resource limits are as follows: 4C and 3L. 2.

Part 4: Series Method (40 points) Solve this resource scheduling problem with the series method. The resource limits are as follows: 4C and 3L. 2. 613 8 11 11 19 1L Activity CS Duration LS 0 11 D 3 14 15 012 17 0 2 117 12 12 19 Resources 0 12 A 0 0 B 22 20 4 4.40 5 3 4004 SOTOS 11 00111 3C, 2L 10, 3L 2L 20012 G K o 11 2 11 13 6 13 1300 113 19 T0 19 2C, 3L 1C, 2L M 19 119 200 10 20 10 10 0 E H 2 2 12 o 43 14 0 2 2 17 40 10 14 70 1017 9 10 10 19 20 1C, 1L 2C, 1L