Question: Part 5 : ( 4 marks ) A drilling machine at Roof Engineering Company has a pile of on average 6 0 parts that needs

Part 5: (4 marks) A drilling machine at Roof Engineering Company has a pile of on average 60 parts that needs drilling work. A new part (that also needs drilling work) is being added to that pile every 2 minutes. Same arival pattern was observed for the parts that are already in the pile.
For how long, a part shall be in the pile before it is drilled?
Hint: Little's Law: Imventony =(Throughput rate)**(Cycle time)
Answer: