Question: Part - A: ( 4 Questions, 1 mark each ) A . 1 : What does the following relationship mean? a . Activity B has
Part A: Questions, mark each
A: What does the following relationship mean?
a Activity B has to start immediately after the start of A
b Activity B can start at least days after the start of
c Activity B can start at most days after the start of A
A: What does the following relationship mean:
a Activity has to finish exactly days after the finish of
b Activity B can finish at least days after the finish of
c Activity B can finish at most days after the finish of A
A: What does the following relationship mean:
a Activity B can start after the start of A and but has to finish at least days before the finish of
b Activity can start before the start of A but has to finish at most days after the finish of
c Activity B can start after the start of A and but has to finish at least days after the finish of A
A: What does the following relationship mean:
a Activity A can start days before the start of activity B
b Activity B can start days after the completion of activity A
c Activity B can start days before the completion of activity A
A: If and are three activities connected with and combination relationships with no lags. Their durations are and ; respectively. What is the duration of the project:
a days.
b days.
c days.
d days.
A: If and are three activities connected with and combination relationships with day lag on the SS relationships only. Their durations are and ; respectively. What is the duration of the project:
a days.
b days.
c days.
d days.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock