Question: Part A is made from 2 Part C's and 2 Part D's. The lead time for each item is 1 week. The batch size for

Part A is made from 2 Part C's and 2 Part D's.

Part A is made from 2 Part C's and 2 Part D's. The lead time for each item is 1 week. The batch size for Assembly A is LFL. Part C is made in lots of 60. Part D is made in lots of 120. Prepare a release schedule for Part C based on the information. Your answer is complete showing the release schedule by week for Part D. No other information is required. Week ITEM:Assembly A 3 4 LFL Order Amt Gross Requirements L 50 50 50 125 On Hand 150 L ITEM: Part C (2 per) Lot size 60 Gross Requirements On Hand 150 ITEM: Part D (2 per) Lot size 120 Gross Requirements On Hand 200 0