Question: Part A ) You serve as the assistant project manager to Reza Kia, who leads the Muscat light project. Muscat light is the codename assigned
Part A
You serve as the assistant project manager to Reza Kia, who leads the Muscat light project. Muscat light is the codename assigned to the creation of a handheld electronic medical reference guide intended for emergency medical technicians and paramedics requiring quick reference materials in emergency situations.
Reza and his project team are crafting a project plan with the goal of producing operational models in time for MedOmn, the largest annual medical equipment trade show. Meeting the critical October deadline for MedOmn is imperative, as this event serves as a platform for major medical equipment manufacturers to showcase and take orders for new products. Reza is aware of rumors suggesting that competitors may be considering similar products, recognizing that being the first to market would confer a significant sales advantage. Additionally, securing funding from top management is contingent upon devising a viable plan to meet the MedOmn deadline.
The project team spent the morning drafting the schedule for Muscat light, starting with the Work Breakdown Structure WBS and expanding it into a network by incorporating activities as necessary. They then incorporated time estimates for each activity. Below is the preliminary information detailing the duration of activities and their predecessors.
Activity Description Duration Predecessor
Architectural decisions None
Internal specifications
External specifications
Feature specifications
Voice recognition
Case
Screen
Speaker output jacks
Tape mechanism
Database
Microphonesoundcard
Pager
Barcode reader
Alarm clock
Computer IO
Review design
Price components
Integration
Document design
Procure prototype components
Assemble prototypes
Lab test prototypes
Field test prototypes
Adjust design
Order stock parts
Order custom parts
Assemble first production unit FS time units
FS time units
Test unit
Produce units
Train sales representatives
Use Microsoft Project program available in SQU labs to develop the schedule for activitiesnoting late and early times, the critical path, and estimated completion for the project.
Prepare a short memo that addresses the following questions:
Will the project as planned meet the October deadline?
What activities lie on the critical path?
How sensitive is this network?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock