Question: Part B (04 Marks) Activities Predecessor Optimistic Most Likely Pessimistic 3 6 12 B 5 9 13 A 2 6 11 D E, C,G 3

Part B (04 Marks) Activities Predecessor

Part B (04 Marks) Activities Predecessor Optimistic Most Likely Pessimistic 3 6 12 B 5 9 13 A 2 6 11 D E, C,G 3 5 9 E 5 7 12 F D, B 7 10 14 G 1 3 6 H G 2 5 I D 7 11 15 J F, I 4 7. 12 K H.J 5 5 10 Consider three point Estimates for this part? 7. Calculate the expected time of critical path? 8. Calculate the variance of all paths? 7/7