Question: PART B- ESSAY. Write your answer in the space provided or on a separate sheet of paper. 21. A network consists of the activities in

PART B- "ESSAY. Write your answer in the space
PART B- "ESSAY. Write your answer in the space provided or on a separate sheet of paper. 21. A network consists of the activities in the following list. Times are given in weeks. PI Activity A Be Ce De E FA Preceding Time 84 32 AP ze A, BE Be ce 42 De 62 tt a. b. Draw the network diagram. Calculate the ES, EF, LS, LF, and Slack for each activity. What is project completion time? C. t