Question: Part b , what is the critical path? 1 2 4 6 8 9 1 2 5 6 8 9 1 2 5 7 8
Part b what is the critical path?
part b
What are the earliest start ES time, latest start LS time, earliest finish EF time, latest finish LF time, and slack time of activity
part b
What are the earliest start ES time, latest start LS time, earliest finish EF time, latest finish LF time, and slack time of activity
part c
What is the expected project duration?
part d
What is the expected project duration?
part d
What is the latest finish time of activity D
part d
What is the earlier start time of activity E
part d
Which activity has the biggest slack time?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
