Question: part c? Consider a process consisting of three resources. Assume there exists unlimited demand for the product Resource 1 has a processing time of 2

 part c? Consider a process consisting of three resources. Assume there part c?

Consider a process consisting of three resources. Assume there exists unlimited demand for the product Resource 1 has a processing time of 2 minutes per unit. Resource 2 has a processing time of 3 minutes per unit. Resource 3 has a processing time of 7 minutes per unit. Resource 1 Resource 2 Resource3 All three resources are staffed by one worker. The flow diagram is shown above Round 'Capacity of resource" to 3 decimal places and other numbers to whole numbers 0.333 units per minute 3 Resource percent a. What is the capacity of resource 2? b. What is the bottleneck in the process? c. What is the utilization of resource 2? d How long does it take the process to produce 205 units starting with an empty system, assuming this is a worker-paced process? 1.440 minutes

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!