Question: Part d got cut off. It asks what is the estimated total cost for this operation? 14_15 Assignment Production Volume (units) Total Cost ($) 400
Part d got cut off. It asks what is the estimated total cost for this operation?

14_15 Assignment Production Volume (units) Total Cost ($) 400 4,100 450 5,100 550 5,500 600 6,000 700 6,500 750 7,100 a. Compute b1 and bo (to 1 decimal). b1 bo Complete the estimated regression equation (to 1 decimal). y = b. What is the variable cost per unit produced (to 1 decimal)? c. Compute the coefficient of determination (to 3 decimals). Note: report r between 0 and 1. = What percentage of the variation in total cost can be explained by the production volume (to 1 decimal)? % d. The company's production schedule shows 500 units must be produced next month. What is the estimated total cost for O X 85.F Mostly sunny