Question: Part d only, slack time for each activity? The following is a table of activities associated with a project at Rafay Ishfaq's software firm in

Part d only, slack time for each activity?
The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations and what activities each must precede: Duration (weeks) 2 3 Precedes B.C E Activity A (start) B C E F(end) 8 4 F 2 This exercise contains only parts b, c, and d. b) The activities on the critical path are A-C-F c) The total project completion time for Rafay Ishfaq's software firm is 12 weeks. (Enter your response as a whole number.) d) Determine the slack time for each of the activities. (Enter your responses as whole numbers.) Slack Time (weeks) Activity AStep by Step Solution