Question: Part I: Effective cost per hour - 1 shift ( 8 hours) per day - 5 holidays - 7 days of vacation - Fringe: 37%

Part I: Effective cost per hour - 1 shift ( 8
Part I: Effective cost per hour - 1 shift ( 8 hours) per day - 5 holidays - 7 days of vacation - Fringe: 37% of base wage - Base hourly wage: $12.50 per hour - 30-minute lunch (paid) plus two 15-minute breaks (paid) per day 1. What is the effective cost per hour per employee? ( 50 points)