Question: Part IV Bottleneck Analysis TS Manufacturing Corp. has the process displayed below. The drilling operation occurs separately from and simultaneously with the sawing and sanding

Part IV Bottleneck Analysis
TS Manufacturing Corp. has the process displayed below. The drilling operation occurs separately from and simultaneously with the sawing and sanding operations. The product only needs to go through one of the three assembly operations (the assembly operations are "parallel")
a) Which operation is the bottleneck? (10 pts)
b) What is the throughput time for overall system? (10 pts)
c) If the firm operates 8 hours per day, 20 days per month, what is the daily capacity of the manufacturing process? (10 pts)
d) What is the efficiency of Welding? (10 pts)
 Part IV Bottleneck Analysis TS Manufacturing Corp. has the process displayed

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!