Question: Part Two: Using Critical Project Management Tools Answer the following questions , using as much space as you need. Witclm) Let's reinterpret the resource demands

Part Two: Using Critical Project Management Tools Answer the following questions , using as much space as you need. Witclm) Let's reinterpret the resource demands over time for a leftjustied schedule assuming you have five people available . Create a left-justified schedule for the project above, assuming ve people, and answer the following questions . 1. Map the earliest start times for each activity to the resource demands over time. What are the earliest start times for each activity? 2. Level the schedule so it is consistent with resource availabilities . What is the new project duration
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
