Question: Part V: Scenario Analysis Use this information to answer questions 31- 34. Suppose BearKat Enterprises management team decides to do a scenario analysis. They want
Part V: Scenario Analysis
Use this information to answer questions 31- 34.
Suppose BearKat Enterprises management team decides to do a scenario analysis. They want you to calculate the expected NPV, standard deviation, and coefficient of variation for a new project. (These are not the NPVs that you calculated earlier). They give you the following data:
- Best case has a 15% probability and has an NPV of $28.95 M.
- Base case has a 55% probability and has an NPV of $17.55M.
- Worst case has a 30% probability and has an NPV of -$35.77M.
QUESTION 31
Use the information given for part V; Scenario analysis.
What is the expected NPV of this project?
| A. | $3.26M | |
| B. | $4.87M | |
| C. | $5.53M | |
| D. | $20.76M |
QUESTION 32
Use the information given for part V; Scenario analysis.
What is the standard deviation of the NPVs of this project?
| A. | $18.795M | |
| B. | $22.317M | |
| C. | $25.85M | |
| D. | $38.154M |
QUESTION 33
Use the information given for part V; Scenario analysis.
What is the coefficient of variation of the NPVs of this project?
| A. | 2.25 | |
| B. | 3.22 | |
| C. | 4.86 | |
| D. | 7.92 |
QUESTION 34
A project that has a coefficient of variation of NPVs of 6.7 is less risky than a project that has a coefficient of variation of NPVs of 2.1.
True
False
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
