Question: PART1 : Given the following activity assumptions table: Immediate Duration Activity Predec. (Days) Name A -- 6 Pre-project B -- 2 Market study C A

PART1 :
Given the following activity assumptions table:
Immediate Duration
Activity Predec. (Days) Name
A -- 6 Pre-project
B -- 2 Market study
C A 3 Feasibility study
D A 5 Realization
E A 3 Definition of marketing policy
F C 2 Cost estimation
G D 3 Prototypes presentation to the customer
H B,E 4 Determination of the cost of the product
I H 2 Evaluation of the turnover
J F,G,I 2 Synthesis report before the start of the series
- Draw the CPM network adding the following information: Activity time, Duration, Early Start Time (ES), Early Finish time (EF), Late Start time (LS), Late Finish time (LF), Slack (4pt)
- Analyze the paths through the network and find the critical path (1pt)
- Calculate the total slack time in the network (2pts)
- Explain briefly, What would you do different if you were asked to use PERT method instead of CPM method? (3pts)