Question: partial credit,Problem 3.15 Question Help Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine
| partial credit,Problem 3.15 | Question Help
|
Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times:
| Activity | Time (weeks) | Immediate Predecessor(s) | Activity | Time (weeks) | Immediate Predecessor(s) |
| A | 6 | minus | E | 3 | B |
| B | 7 | minus | F | 5 | B |
| C | 3 | A | G | 10 | C, E |
| D | 1 | A | H | 6 | D , F |
Dave's earliest start (ES) and earliest finish (EF) are:
| Activity | ES | EF |
| A | 00 | 55 |
| B | 00 | 77 |
| C | 55 | 99 |
| D | 55 | 66 |
| E | 77 | 1212 |
| F | 77 | 1313 |
| G | 1212 | 2121 |
| H | 1313 | 2020 |
Dave's latest start (LS) and latest finish (LF) are:
| Activity | LS | LF |
| H | 1414 | 2121 |
| G | 1212 | 2121 |
| F | 88 | 1414 |
| E | 77 | 1212 |
| D | 1313 | 1414 |
| C | 88 | 1212 |
| B | 00 | 77 |
| A | 33 | 88 |
The slack times are:
| Activity | Slack |
| A | 33 |
| B | 00 |
| C | 33 |
| D | 88 |
| E | 00 |
| F | 11 |
| G | 00 |
| H | 11 |
The activities on the critical path are
B - E - G
.The total project completion time for Dave =
2121
weeks.
Question is complete. Tap on the red indicators to see incorrect answers.
| Similar Question
|
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
