Question: partial credit,Problem 3.15 Question Help Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine

partial credit,Problem 3.15

Question Help

Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times:

Activity

Time (weeks)

Immediate Predecessor(s)

Activity

Time (weeks)

Immediate Predecessor(s)

A

6

minus

E

3

B

B

7

minus

F

5

B

C

3

A

G

10

C, E

D

1

A

H

6

D , F

Dave's earliest start (ES) and earliest finish (EF) are:

Activity

ES

EF

A

00

55

B

00

77

C

55

99

D

55

66

E

77

1212

F

77

1313

G

1212

2121

H

1313

2020

Dave's latest start (LS) and latest finish (LF) are:

Activity

LS

LF

H

1414

2121

G

1212

2121

F

88

1414

E

77

1212

D

1313

1414

C

88

1212

B

00

77

A

33

88

The slack times are:

Activity

Slack

A

33

B

00

C

33

D

88

E

00

F

11

G

00

H

11

The activities on the critical path are

B - E - G

.The total project completion time for Dave =

2121

weeks.

Question is complete. Tap on the red indicators to see incorrect answers.

All parts showing

Similar Question

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!