Question: Partitioning tasks with broad implicit scope to increase specificity is a method to reduce the likelihood of the ______ project planning pitfall. A. problems associated
Partitioning tasks with broad implicit scope to increase specificity is a method to reduce the likelihood of the ______ project planning pitfall.
A. problems associated with task durations
B. tasks that focus on work rather than deliverables
C. insufficient task granularity
D. internally inconsistent estimates