Question: Partitioning tasks with broad implicit scope to increase specificity is a method to reduce the likelihood of the ______ project planning pitfall. A. problems associated

Partitioning tasks with broad implicit scope to increase specificity is a method to reduce the likelihood of the ______ project planning pitfall.

A. problems associated with task durations

B. tasks that focus on work rather than deliverables

C. insufficient task granularity

D. internally inconsistent estimates