Question: Path level uncertainty are uncertainties associated with the Critical Path. Using the three time estimates for each activity, calculate the probability that the critical path

Path level uncertainty are uncertainties associated with the Critical Path. Using the three time estimates for each activity, calculate the probability that the critical path activities will be completed within a specified time, in this case, 90 days. Activity A 12/18/42 Activity B 18/33/60 Activity C 8/11/20+11
 Path level uncertainty are uncertainties associated with the Critical Path. Using