Question: PATH SLACK A 4C 6H 6 ACFHJ 0 . 6H 5 6 ABFHJ 2 3 6 ACFIJ START DID 4 B 4C 4B 4 B

PATH SLACK A 4C 6H 6 ACFHJ 0 . 6H 5 6 ABFHJ 2 3 6

PATH SLACK A 4C 6H 6 ACFHJ 0 . 6H 5 6 ABFHJ 2 3 6 ACFIJ START DID 4 B 4C 4B 4 B 4 B 6 F 4F 6 F 4 F 4D 4E 60 61 316 DURATION 4+6+6+6+6=28 4+4+6+6+6=26 4+6+6+3+6+25 4+4+6+3+6=23 4+4+3+2+6=19 4+4+1+2+6=17 6) 6) 3) 3) 2) 2) FINISH 6 ABFIJ 5 6 ABDGJ 9 A 1 G 6 ABEGJ 11 Consider the project above ACFHJ 1. calculate the duration for each path 2. identify the critical path 3. calculate the project duration 4. calculate the slack for each path 5. enter in the table below the activity slacks Activity Slack A 0 B 0 C D E F G H 1 J 0