Question: Paused B Rollout plan Change management plan Change control plan D Project management plan You are managing a project to implement a business change to

Paused
B Rollout plan
Change management plan
Change control plan
D Project management plan
You are managing a project to implement a business change to your organization. In doing so, you are documenting the plan for knowledge transfer, training, and readiness activities required to implement the business change. Which document are you updating?
A Rollout plan
B Change management plan
C Change control plan
D Project management plan