Question: PE 1 2 - 5 . Per the I 2 C 2 embedded clinics / pharmacies ( ECP ) business case, I 2 C 2
PE Per the IC embedded clinicspharmacies ECP business case, IC is considering a series of enhancements to this
existing system. In planning discussions with IC business and IT team members, the following points were captured in the
meeting minutes. Complete the following for each of these points: Determine if the item is a risk, and issue, an assumption,
or a constraint. For risks and issues, determine the level of impact high medium, or low and relate it to a corresponding
item in Table For risks, determine the level of probability high medium, or low and your preferred mitigation
strategy avoidance limitation transference, or acceptance For each item, explain your answers.
a Given the dozen countries in which IC operates clinicspharmacies management decided to let three senior pharmacy
leaders in Mexico, Ethiopia, and Malaysia be product owners on behalf of the rest of the world.
b The prior point did raise a concern that those three leaders might not be able to speak for users in the other nine countries,
given differences in legal regulations and market practices in different parts of the world.
c Further, it was just determined that one of those three senior pharmacy leaders will be going out on paternity leave for two
months.
d In discussing the sharing drugs feature, there was some disagreement regarding whether IC pharmacies should be able
to share drugs across national borders. In several geographically small countries in Central America, pharmacists noted that
IC pharmacies in different countries were only a few miles apart. The costestimation impacts of this could be large.
e For sharing drugs and consolidated purchasing, the system is currently built with each pharmacy running its own instance of
the system using a local database. This will necessitate implementing a new architecture using a centralized database, either
replacing the existing local databases or maintaining copies of that data.
f The IC team has historically underestimated the time and cost needed to develop features. Because of this, the CIO is
requiring improved training on project estimation, planning, and management.
g Also, the CIO noted that IC has historically utilized several key outside contractors, each of whom understands the IC
pharmacy system thoroughly. However, because IC hasnt used those contractors for almost a year, it is not clear if they
will be available for this project.
h This project cannot start for another six weeks, while the development team finishes up another, unrelated project that is
occupying them fulltime.
Step by Step Solution
There are 3 Steps involved in it