Question: PE 6 - 4 . Your team has created the following product backlog. Assume that the stories are independent: they each contribute business value and

PE 6-4. Your team has created the following product backlog. Assume that the stories are independent: they each contribute business value and
can be built in any order. Further, assume that the estimates are in ideal days and that the team has the capacity to complete thirty ideal days of
work per sprint. Based on this, complete the following:
a. Allocate stories to Sprint 1 using the agile sprint-by-sprint planning approach, being sure to respect the thirty-day capacity constraint.
b. Allocate the remaining stories to additional sprints, per hybrid release planning.
c. Determine how many sprints this should take, assuming the estimates are correct.
d. Based on the assumptions provided previously, which makes more sense to use: agile sprint-by-sprint planning or hybrid release planning?
Explain your answer.
 PE 6-4. Your team has created the following product backlog. Assume

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!