Question: People are served in a process with two resources. The first resource has a capacity of 2 people per hour. The capacity of the second

People are served in a process with two resources. The first resource has a capacity of 2 people per hour. The capacity of the second resource is 1.8 people per hour. The first resource has 6 workers and the second resource has 8 workers. Demand for this process is 1.9 people per hour. Wages are $20 per hour.
What is the cost of direct labor (in $)?
Note: Round your answer to 2 decimal places.