Perform a Multi-Atribute Decision analysis using the following utility table and k values. Which combination of Overrun
Fantastic news! We've Found the answer you've been seeking!
Question:
Perform a Multi-Atribute Decision analysis using the following utility table and k values. Which combination of Overrun Time and Extra Cost is the best choice?
Time Overrun | Utility | Cost | Utility | |
0 | 1 | 29000 | 1 | |
2.8 | 0.87 | 43000 | 0.85 | |
3.1 | 0.44 | 50000 | 0.74 | |
5.7 | 0 | 110000 | 0.47 | |
133000 | 0 | |||
k1 = | 0.78 | |||
k2= | 0.5 |