Question: Perform a project management analysis for the data given below to determine ES , EF , LS , LF , and slack for each activity,

Perform a project management analysis for the data given below to determine ES, EF, LS, LF, and slack for each
activity, the total project completion time, and the critical path.
Activity Time (weeks) Predecessors Activity Time (weeks) Predecessors
A 5 E 3 B
B 4 F 5 B
C 1 A G 9 D, E
D 2 A H 6 C, F
(a) Draw a network with t, ES, EF, LS, and LF (follow the same format as Figure 11.5 on p.394)