Question: Perform critical path analysis by finding: a) Earliest start b) Latest start c) Earliest finish d) Latest finish e) Slack f) Critical path Activity Predecessor
Perform critical path analysis by finding:
a) Earliest start
b) Latest start
c) Earliest finish
d) Latest finish
e) Slack
f) Critical path
Activity
Predecessor
Duration (days)
A
-
4
B
A
2
C
A
3
D
B
6
E
C
1
F
C
3
G
D, E
5
H
F, G
2