Question: Perform variance analysis for General Electric's direct labor for August 2023. Item Amount ($) Standard Cost per Hour 16 Actual Cost per Hour 17 Standard
Perform variance analysis for General Electric's direct labor for August 2023.
Item | Amount ($) |
Standard Cost per Hour | 16 |
Actual Cost per Hour | 17 |
Standard Hours Allowed for Actual Production | 2,500 hours |
Actual Hours Worked | 2,700 hours |
Question:
Using the given data, calculate the direct labor rate variance and the direct labor efficiency variance for General Electric for August 2023. Show your calculations and explain the significance of these variances.