Question: Performance Observation ( minutes per cycle ) Element Rating 1 2 3 4 5 Prepare daily
Performance Observation minutes per cycle
Element Rating 
Prepare daily reports

Photocopy results

Label and package reports

Distribute reports
Photocopying machine broken; included as delay in the allowance factor
Power outage; included as delay in the allowance factor
The allowance factor for this type of work is given to be

Round all intermediate calculations to two decimal places before proceeding with further calculations.
Part
a The normal time for the "prepare daily reports" operation 
enter your response here
minutes round your response to two decimal places
Part
The normal time for the "photocopy results" operation 
enter your response here
minutes round your response to two decimal places
Part
The normal time for the "label and package reports" operation 
enter your response here
minutes round your response to two decimal places
Part
The normal time for the "distribute reports" operation 
enter your response here
minutes round your response to two decimal places
Part
The normal time for the overall process 
enter your response here
minutes round your response to two decimal places
Part
b The standard time for this process 
enter your response here
minutes round your response to two decimal places
Part
c The number of observations that are required for a

confidence level within

accuracy 
enter your response here
round your response to the immediate higher whole number
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock