Question: Perssimistic 1 Predecessor Brain Break Optimistic Most likely duration 4 5 4 8 6 7 5 9 4 6 A D BE G 9 9

Perssimistic 1 Predecessor Brain Break Optimistic

Perssimistic 1 Predecessor Brain Break Optimistic Most likely duration 4 5 4 8 6 7 5 9 4 6 A D BE G 9 9 11 10 8 9 10 8 9 8 F 9 2 5 3 5 H 6 6 ta. Calculate the durations for each of the activities using the beta distribution (durations in weeks) 1b. Draw the network diagram using the weighted average and determine the earliest time the project would be completed Q. Determine the activities on the critical path & calculate the standard deviation for the activities on the critical path

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!