Question: PERT HOMEWORK #2 Design a PERT Chart based on the activities below and be sure to include the ECT, LAT, slack time for each node,
PERT HOMEWORK #2
Design a PERT Chart based on the activities below and be sure to include the ECT, LAT, slack time for each node, along with the critical path.
Activity Predecessor Duration (days)
A NONE 7
B NONE 5
C A 3
D A 4
E B 2
F B 3
G C 6
H D, E 2
I F 8
J D, E 5
K G, H 4
L I 3