Question: PERT HOMEWORK #2 Design a PERT Chart based on the activities below and be sure to include the ECT, LAT, slack time for each node,

PERT HOMEWORK #2

Design a PERT Chart based on the activities below and be sure to include the ECT, LAT, slack time for each node, along with the critical path.

Activity Predecessor Duration (days)

A NONE 7

B NONE 5

C A 3

D A 4

E B 2

F B 3

G C 6

H D, E 2

I F 8

J D, E 5

K G, H 4

L I 3