Question: PERT Network Times Draw a project network for this project. Compute the early and late activity times and the slack times. Identify the critical Path
PERT Network Times
Draw a project network for this project. Compute the early and late activity times and the slack times. Identify the critical Path
2.1
| ID | Activity | Predecessor | Time |
| A | Order Review | None | 3 |
| B | Order standard parts | A | 4 |
| C | Produce standard parts | A | 11 |
| D | Design custom parts | A | 14 |
| E | Software development | A | 19 |
| F | Manufacture custom hardware | C,D | 16 |
| G | Assemble | B,F | 11 |
| H | Test | E,G | 6 |
2.2
| ID | Activity | Predecessor | Time |
| A | Prepare Site | None | 3 |
| B | Pour Foundation | A | 4 |
| C | Erect Frame | B | 5 |
| D | Roof | C | 5 |
| E | Windows | C | 2 |
| F | Doors | C | 2 |
| G | Electrical | C | 4 |
| H | Rough-In-Time | D,E,F,G | 3 |
| I | Door Opener | D,E,F,G | 2 |
| J | Paint | H,I | 3 |
| K | Cleaner | J | 2 |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts