Question: (PERT project scheduling) Predecessors Optimistic Time (a) Most Likely Time (m) Pessimistic Time (b) A 0.5 1 1.5 B A 2 4 5 C A

(PERT project scheduling) Predecessors Optimistic Time (a) Most Likely Time (m) Pessimistic Time (b) A 0.5 1 1.5 B A 2 4 5 C A 2 3 6 D A 6 7 8 E B 4 6 7 F C, D 1 2 2.5 G E, F 6 7 9 H D 6 9 11 I G, H 2 4 6 EXPECTED ACTIVITY What are the expected time(E) and the variance of expected time (2) for each activity? Identify the critical path and determine the expected time to complete the project (Ecp). Compute the variance of the critical path duration (cp2). Whatistheprobabilitythattheprojectwillbecompletedin24daysorless? What is the probability that the project will be completed in 21 days or less? What is the probability that the project will be completed in 20 days or more? VARIANCE

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Mathematics Questions!