Question: Peter is the project manager for a large project to build a bridge that links two cities crossing a river. The project has a high-risk
Peter is the project manager for a large project to build a bridge that links two cities crossing a river. The project has a high-risk score. He is working with his team to plan the risk responses for the project to decrease the project risks. He feels that the team successfully completed the risk response planning. Which of the following risk processes is repeated after the plan risk responses to determine if the overall project risk has been satisfactory
a. Perform Quantitative Risk Analysis
b. Identify Risks
c. Plan Risk Responses
d. Perform Qualitative Risk Analysis